Production Order Variance Analysis (KSS2/KKS1)
Total Target Cost
TC
PKR 262,500.00
Based on standard cost estimates
Total Actual Cost
AC
PKR 264,050.00
Settled order costs
Total Variance
-PKR 1,550.00
Unfavorable across all plants
Key Variance Driver
Input Price
Accounted for 60% of deviations